Disabled passengers among 23,000 daily users face 20-fold longer walk to Tube under Edgware bus station demolition plans
Save Our Edgware has formally asked Barnet Council to strengthen the Section 106 agreement and pause the GLA Stage 2 referral.
Why? Because the current outline approval allows the demolition of Edgware Bus Station without securing a safe, equivalent replacement.
🔴 Key Issue: Increased Walking Distances to Tube by 20-fold
The Ballymore’s own Transport Assessment Addendum recognises:
“It is therefore recognised that the proposed bus station arrangements would result in increased walking distances for bus to LU interchanges.”
Under the existing layout, most passengers alight at Stop G immediately next to the Northern line entrance, with a walking distance of around 5 metres.
Under the proposed layout, key interchange stops (GN2, GS2, D2 and E2) would be between 92 metres and 136 metres from the Underground entrance.
That represents a 20+ fold increase in walking distance, rising from around 5 metres today to between 92 and 136 metres under the proposed layout. Such a substantial increase would disproportionately affect older residents, disabled passengers, parents with buggies, people with mobility impairments, and anyone trying to interchange in poor weather conditions.
This is not an improvement. It is a downgrade.
🔴 18 bus stands at risk of permanent loss
The scheme proposes moving 18 bus stands into an underground EV bus garage beneath 9 tower blocks. London Fire Brigade has raised fire safety concerns about the underground garage design, and its safe and lawful operation remains unresolved. However, the approved phasing permits demolition of the existing surface bus station and garage in year 1, before the underground facility is proven capable of safe occupation. This creates a real risk that the current 18 bus stands are removed in year 1, while the proposed underground stands may not be operable, potentially leaving Edgware with reduced capacity and reliance on dispersed on-street stops instead of a functioning integrated station.
🔴 Equality Duty Concerns
TfL, as a public body and landowner, has a statutory duty under the Public Sector Equality Duty in the Equality Act 2010 to properly assess and have due regard to the impact on protected groups.
However, there is no evidence that TfL has carried out a lawful and transparent PSED assessment of the 20+ fold increase in interchange walking distances for disabled passengers and others with mobility impairments.
Approving demolition before securing a guaranteed, accessible replacement risks breaching that duty.
We are asking for one clear safeguard:
👉 No demolition or works that render the existing bus station inoperable unless and until a fully operational, safe, accessible and no worse replacement is delivered.
Regeneration must improve infrastructure, not make it harder for residents to get home.
From: Save Our Edgware <saveouredgware@gmail.
Date: Fri, 20 Feb 2026 at 17:04
Subject: Protect Edgware Bus Station and ensure Equality Duty compliance – Request to enhance Section 106 and pause Stage 2 referral (Application 24/2686/OUT) (Our Ref:SOE20260220)
To: Mclean, Josh (LBB) <Josh.Mclean@barnet.gov.uk>
Cc: redacted
To Josh Mclean and Barnet planning officers, Leader’s Office and Executive Team, Members of the Strategic Planning Committee and Overview and Steering Committee, Councillors at Edgware and Edgwarebury wards and the Chief Executive of Barnet Council
Dear Josh,
We write further to Barnet Council’s resolution to approve planning application 24/2686/OUT (Edgware Town Centre) and the ongoing drafting of the Section 106 agreement.
The existing Edgware Bus Station is a single, off-street, integrated, enclosed and staffed interchange directly adjacent to the Northern line Underground entrance. It comprises 18 stand positions and 5 stops, serves approximately 20 bus routes, and provides a sheltered, enclosed 68-seat waiting environment within a consolidated operational layout. Transfer distances between bus and Underground services are minimal, with many passengers alighting immediately adjacent to the station entrance.
Planning application 24/2686/OUT embeds a fundamental structural change to this arrangement. It provides for demolition of the existing integrated bus station and its replacement with dispersed on-street stops and a looped “Station Square” configuration, with 18 stand positions proposed within an underground EV bus garage dependent upon future fire and building safety approvals.
Against that context, the current proposal would:
- Increase bus-to-Underground walking distances from 5 metres to between approximately 92 and 136 metres;
- Introduce multiple additional signalised crossings and prolonged exposure to live traffic where none are currently required;
- Remove the existing enclosed, staffed 68-seat bus station environment directly adjacent to the Underground entrance;
- Relocate 18 stand positions into an underground facility lacking confirmed fire safety approval, creating a real risk of permanent loss of stand capacity; and
- Proceed without clear evidence that the Council has lawfully discharged its Public Sector Equality Duty in respect of these impacts.
Taken together, these changes represent a material downgrade of a strategic public transport interchange and raise serious development plan and public law concerns.
The adopted Barnet Local Plan 2021–2036, under “B. New Public Transport Infrastructure”, expressly requires in relation to Edgware:
“f) Interchange improvements at Edgware with protection or re-provision of bus operations and bus station function as part of any redevelopment. London Underground infrastructure and operations must also be maintained.”
This is not an aspiration. It is a binding development plan requirement that interchange must be improved, bus operations must be protected or re-provided, bus station function must be protected or re-provided, and London Underground infrastructure must be maintained.
Under section 38(6) of the Planning and Compulsory Purchase Act 2004, decisions must be made in accordance with the development plan unless material considerations indicate otherwise.
The proposal removes the existing enclosed 68-seat integrated bus station and replaces it with a fragmented street-based arrangement involving walking distances of up to 136 metres, additional pedestrian crossings, and relocation of 18 stand positions into an underground garage dependent upon unresolved fire safety approvals.
The increase in walking distance — over twenty times the current interchange distance experienced at Stop G — cannot reasonably be characterised as an “interchange improvement”. It constitutes a material downgrade in accessibility, convenience, safety and integration, particularly for disabled people, older residents, pregnant passengers and those with reduced mobility.
The introduction of multiple signalised crossings and extended exposure to live carriageways similarly represents a reduction in interchange safety and legibility compared to the current off-street integrated station environment.
If fire safety approval for the underground garage is delayed or refused, the proposed underground stands cannot lawfully operate, yet the existing 18 surface stands will already have been demolished. This creates a foreseeable and potentially irreversible risk of permanent loss of stand capacity, contrary to the Local Plan requirement for protection or re-provision of bus station function.
These impacts also raise serious concerns as to whether the Council has lawfully discharged its Public Sector Equality Duty under section 149 of the Equality Act 2010, given the disproportionate effect that longer walking distances, multiple crossings and loss of an enclosed staffed interchange will have on people with protected characteristics.
Residents have consistently stated that redevelopment must not result in the loss or downgrade of essential public transport infrastructure. The expectation of transport enhancement has instead resulted in longer walking distances, fragmented interchange, removal of a protected waiting environment, and a real risk of permanent capacity loss.
Notwithstanding the Committee resolution:
- Planning permission has not yet been issued;
- The Section 106 agreement has not been completed; and
- The application has not yet been referred for Stage 2 determination.
The Council therefore retains full authority — and a continuing legal duty — to ensure compliance with the development plan and equality law before finalising the Section 106 agreement.
To prevent the permanent loss or downgrade of bus station function, and to ensure compliance with the adopted Local Plan requirement under “B. New Public Transport Infrastructure”, we formally request that the following obligation is included in the Section 106 agreement.
This request does not reopen the principle of development resolved by Committee. It is a targeted safeguard to ensure that redevelopment remains infrastructure-led, deliverable and lawful, and that interchange improvements are genuine rather than illusory.
The requested obligation is necessary to ensure compliance with:
- The National Planning Policy Framework requirement that development is deliverable and supported by appropriate infrastructure;
- London Plan policies safeguarding public transport interchanges, accessibility and inclusive design;
- The Council’s duty to avoid approving development that results in a material downgrade of public transport provision; and
- The Public Sector Equality Duty under section 149 of the Equality Act 2010.
————————————————————————————————————
Proposed Section 106 Obligation – Edgware Bus Station (Risk-Mitigated and Binding)
The Owner covenants with the Local Planning Authority that no demolition, enabling works, excavation, decant, or works rendering the Existing Edgware Bus Station or Bus Garage wholly or partly inoperable shall take place unless and until a final Bus Station Solution has been approved in writing by:
- the Local Planning Authority in consultation with Transport for London;
- the London Fire Brigade (in respect of fire safety);
- the Building Safety Regulator; and
- the Health and Safety Executive (where applicable),
and such written approvals confirm that:
- all applicable fire safety, building safety and operational regulatory requirements have been satisfied; and
- the proposed bus arrangements provide stand capacity, operational resilience, interchange efficiency and passenger environment no worse than the Existing Bus Station; and
- the Replacement Bus Station is capable of lawful occupation and safe operational public use.
For the avoidance of doubt, anticipated, conditional, phased or future approvals shall not satisfy this obligation.
For the purposes of this obligation, a “Bus Station Solution” shall mean either:
- the retention of the Existing Edgware Bus Station in a fully operational state; or
- the delivery of a Replacement Bus Station complying with the requirements below.
Any Replacement Bus Station shall provide facilities and operational characteristics no worse than the Existing Bus Station, including (without limitation):
1. Stand Capacity and Operational Integrity
- No fewer than 18 independently operable stand positions.
- Stand layouts shall not permit stacking that obstructs or encroaches upon pedestrian crossings (including prevention of the defect identified as Stand F2 stacking and crossing obstruction in the Addendum).
- Termination capacity shall be sufficient to prevent carriageway obstruction caused by single-bay termination constraints (including prevention of the defect identified as GS2 termination capacity failure and carriageway obstruction).
- Operational resilience and layover capacity shall prevent stacking onto Station Road under peak clustering conditions.
- The layout shall not introduce sequential manoeuvres involving stop–turn–crossing–stand–merge movements materially greater than the Existing off-road configuration (addressing the sequential stop and signal conflict defect identified in the Addendum).
2. Interchange Distance and Layout
- An integrated off-street interchange layout (not dispersed or looped on-street stops).
- Interchange walking distance between principal alighting points and the Underground entrance no worse than the current Stop G arrangement (approximately 5 metres).
- In any event, a maximum walking distance of no more than 15 metres, measured along a direct, accessible, step-free route.
- No additional pedestrian crossings beyond those currently required for interchange.
- No extended walking along live carriageways.
Walking distances in the order of 92–136 metres (as identified in the Addendum in relation to GN2, GS2, D2 and E2) shall constitute non-compliance.
3. Shelter and Passenger Environment
- Enclosed, weather-protected waiting accommodation.
- Enclosed waiting floor area no less than existing provision and no fewer than 68 enclosed seats.
- Continuous structural weather protection between boarding areas and the Underground entrance.
- Waiting areas shall not be directly exposed to live carriageways.
- Open-air islands, partial canopies or dispersed shelters shall not constitute compliance (addressing the reduced shelter and fragmented waiting defect identified in the Addendum).
4. Accessibility and Boarding Conditions
- Fully step-free access throughout.
- Lay-by widths of not less than 3.6 metres clear operational width, preventing the narrow lay-by condition (approximately 2.5 metres) identified in the Addendum.
- Publicly accessible toilet and welfare facilities.
- Real-time bus and Underground passenger information.
- Staffing and supervision arrangements are no worse than existing provision.
5. Regulatory Approval and Underground Garage Safeguard
The Replacement Bus Station shall be capable of lawful operation and comply with all applicable fire safety, building safety and operational regulatory requirements.
Where any bus stand capacity is proposed within an underground bus garage:
- Demolition of the Existing Bus Station or Bus Garage, and commencement of excavation or construction, shall not take place unless and until both interim and permanent bus arrangements have been approved in writing by:
- the London Fire Brigade;
- the Building Safety Regulator;
- the Health and Safety Executive (where applicable); and
- the Local Planning Authority in consultation with Transport for London;
- Such approvals shall confirm compliance with fire safety, building safety and adequacy of bus service provision.
- No underground bus stand capacity shall be relied upon unless and until all such approvals have been formally granted and the facility is capable of lawful and safe operational use (addressing the risk identified in the Addendum of permanent loss of the 18 underground stands).
For the avoidance of doubt:
- Dispersed, temporary or permanent on-street stops shall not constitute a Bus Station Solution.
- Demolition shall not be triggered by anticipated, conditional or future approvals.
<End of Section 106 text.>
Conclusion
We strongly urge the Council to include the above obligation in the Section 106 agreement before it is finalised or referred for Stage 2 determination. Failure to do so would risk locking in the permanent loss of a critical public facility and expose the Council to avoidable planning and public law risk.
We look forward to your confirmation that this matter will be addressed as a priority.
For ease of reference, we attach a copy of the correspondence sent today to the TfL Monitoring Officer.
We would be grateful if you could confirm how the Council proposes to proceed.
We look forward to hearing from you.
Yours sincerely,
Anuta
on behalf of Save Our Edgware
Addendum – The proposed replacement bus arrangements constitute a fundamental downgrade of Edgware’s existing integrated interchange and risk permanent loss of bus station function
1. Edgware is a major strategic interchange – this is not a minor local stop
Development Plan Requirement – Protection or Re-Provision of Bus Station Function
The adopted Barnet Local Plan 2021–2036 expressly requires, in relation to Edgware:
“f) Interchange improvements at Edgware with protection or re-provision of bus operations and bus station function as part of any redevelopment. London Underground infrastructure and operations must also be maintained;”
This policy requirement is clear and unambiguous. It requires:
- Interchange improvements;
- Protection or re-provision of bus operations;
- Protection or re-provision of bus station function; and
- Maintenance of London Underground infrastructure and operations.
The demolition of the existing integrated bus station, its replacement with dispersed on-street stops, and the relocation of 18 stand positions into an underground facility that has not secured fire safety approval raises serious concerns as to whether the scheme complies with this adopted development plan requirement.
A scenario in which the existing 18 surface stands are demolished before the underground facility is demonstrably capable of lawful and safe operation cannot properly be described as “protection or re-provision” of bus station function. It instead introduces a real risk of permanent loss of stand capacity, contrary to the express wording of the Local Plan.
Under section 38(6) of the Planning and Compulsory Purchase Act 2004, planning decisions must be made in accordance with the development plan unless material considerations indicate otherwise. The downgrade and capacity risk embedded in the current proposal therefore engages direct development plan conflict.
Barnet Council has resolved to approve the outline application and is drafting the Section 106 agreement prior to referral to the Mayor of London for Stage 2 determination. The strategic decision embedded in the outline permission is the removal of the existing integrated Edgware Bus Station and its replacement with dispersed on-street stops and a looped “Station Square” island configuration, with additional stand capacity proposed within an underground bus garage.
This is not a minor design adjustment. It is a fundamental change to the nature, quality and safety of the interchange.
Edgware functions as a major public transport hub and multi-modal interchange. The existing bus station comprises 18 stands and 5 stops, serves approximately 20 bus routes, and is the one of the busiest bus stations in North London. The associated bus garage accommodates around 190 buses and approximately 700 operational staff. This demonstrates that Edgware is not a minor local stop but a strategically significant interchange within TfL’s network, supporting high-capacity bus-to-underground interchange and serving a wide catchment across Barnet, Harrow and beyond. Any material alteration to its structure, capacity or operational resilience therefore engages strategic transport network considerations under London Plan Policy T3, not merely local design adjustments.
2. The existing bus station provides a protected, integrated and efficient interchange
The existing bus station is a single, off-road, consolidated bus station directly adjacent to the Underground entrance. It provides:
- four covered boarding bays with 68 seats
- one dedicated alighting bay
- approximately 15 bus stands (18 stand positions)
within a sheltered, communal and staffed environment. Transfer distances between bus and Tube are minimal, and a substantial proportion of passengers alight immediately adjacent to the underground station entrance.

3. The proposed scheme replaces an integrated bus station with a fragmented street-based layout
By contrast, the proposed arrangement:
- disperses bus stops along Station Road and around a looped island
- relocates alighting functions to multiple points including Approach Road
- increases interchange walking distances from less than 5 metres to approximately 100–150 metres
- introduces additional pedestrian crossings and exposure to live traffic
- removes the enclosed, centralised waiting environment
- replaces a consolidated interchange with a fragmented, signal-constrained street-based configuration
The fragmentation of stops, longer walking routes and exposure to open street conditions represent a material downgrade in interchange quality, particularly for disabled people, older residents, pregnant passengers and those with reduced mobility.
4. Detailed explanation of operational and passenger safety defects
- Significant Increase in Bus-to-LU Interchange Distance – Acknowledged by the Applicant
Under the existing arrangement, most buses alight at Stop G, which is located immediately adjacent to the entrance to Edgware LU station. This provides an exceptionally short and direct interchange distance, enabling passengers to step off a bus and enter the Underground station within only a few metres.
The Applicant’s own Transport Assessment Addendum (Section 5.3.5) confirms:
“It is therefore recognised that the proposed bus station arrangements would result in increased walking distances for bus to LU interchanges.”
Under the proposed layout:
- New bus stops GN2, GS2, D2 and E2, which accommodate the greatest levels of bus-to-rail interchange, are located between 92 metres and 136 metres from the LU station entrance.
- This represents an increase of approximately 20+ times the current interchange distance experienced by passengers alighting at Stop G.
From a passenger safety perspective, this means longer exposure in open public highway conditions, increased fatigue for vulnerable users, and greater risk of slips, trips and falls. The impact is particularly severe for disabled people, elderly users, pregnant passengers and those with mobility impairments, who rely on short, direct and protected interchange routes.

- Reduced shelter and dispersed waiting increasing unsafe behaviour
The existing integrated station provides a consolidated, sheltered waiting environment with 68 seats. The dispersed layout materially reduces sheltered capacity. In adverse weather, passengers are likely to wait under the Underground canopy and then cross at short notice when buses arrive. This behavioural pattern increases the risk of signal non-compliance and unsafe crossings. - Increased road crossings and exposure to live traffic
Many transfers will now require one or two signalised crossings within Station Square or along Station Road. The current arrangement allows many passengers to transfer without crossing live traffic lanes. The new layout increases pedestrian severance, increases exposure to moving vehicles, and elevates the likelihood of conflict between buses and pedestrians.
- 4 additional sequential stops and increased signal conflict creating collision risk
Buses entering Station Square must stop to turn in, stop at a crossing, stop at a stand, and then stop again to merge back onto Station Road. This repeated stop sequence does not exist in the current off-road bus station. It materially increases signal interaction complexity, driver workload, congestion, and the probability of pedestrian-vehicle conflict. - Stand F2 stacking risk and crossing obstruction
The length of Stand F2 is insufficient to allow two buses to operate independently. If a second bus arrives while the first remains at the stand, the rear bus may block or encroach upon a pedestrian crossing. This creates an avoidable pedestrian collision hazard and increases the likelihood of unsafe informal crossings. - GS2 termination capacity failure and carriageway obstruction
Stop GS2 can accommodate only one bus at a time, yet five routes are proposed to terminate there. If a second bus arrives while the first is still dwelling, the carriageway may be obstructed. This creates stacking, blocks sightlines, and increases the risk of pedestrian exposure in constrained traffic conditions. - Lane merge bottleneck increasing conflict risk
After the second crossing within Station Square, two lanes merge into one. This creates a departure bottleneck. From a safety perspective, this increases stacking, reduces predictability of vehicle movements, and heightens the risk of sudden braking and vehicle-pedestrian interaction. - Signalised stacking and back-up onto Station Road causing congestion
If a crossing signal is red and the stand is occupied, buses may be unable to exit, creating the potential for stacking back onto Station Road. Congested conditions increase driver stress, reduce reaction times and create unpredictable movement patterns. The modelling appears to rely on average buses-per-hour assumptions and does not robustly stress-test clustering, dwell variability or peak passenger surges. - Accessibility non-compliance increasing boarding risk
The proposed layby width is approximately 2.5 metres, whereas inclusive design guidance such as BS 8300-1:2018 recommends approximately 3.6 metres for accessible boarding conditions. Reduced width increases risk for wheelchair users, mobility scooter users and visually impaired passengers during boarding and alighting, particularly in high passenger volumes.
Taken together, these changes represent a measurable downgrade in passenger safety and operational resilience.
5. Moving 18 Bus Stands underground risks losing them permanently
In addition, 18 stand positions are proposed within an underground EV bus garage beneath 9 tower blocks. However, the London Fire Brigade has raised fire safety concerns regarding the underground garage design, and its safe and lawful operation remains unresolved.
The approved phasing permits the demolition of the existing surface bus station and garage before the underground 18 stand garage is demonstrably capable of occupation and safe operation.
This creates a material risk that:
- the existing 18 stand positions will be demolished in year 1
- the proposed 18 underground stands may not be capable of occupation due to unresolved fire safety issues
- Edgware may be left with reduced or compromised stand capacity, dependent upon dispersed on-street stops rather than a functioning integrated station
This phasing risk compounds the interchange downgrade and raises serious questions of deliverability, safety and public transport resilience.

Conclusion:
The proposed bus arrangements do not represent an enhancement of existing infrastructure. They constitute:
- A reduction in interchange quality
- A downgrading of passenger environment
- A material operational risk
- A capacity risk tied to unresolved fire safety approvals
- A fragmentation of a currently coherent metropolitan interchange
These defects are embedded at outline stage and cannot be remedied through Reserved Matters.
They are therefore fundamental planning issues, not matters of design refinement.
Comparative Assessment – Existing vs Proposed Interchange
| Key Issue | Existing Integrated Bus Station | Proposed Arrangement |
| Walking distances increased up to 10–15 times (10m → 92–136m) | Approximately 5 metres from Stop G directly into the Underground entrance | Between 92 and 136 metres for key interchange stops (GN2, GS2, D2, E2), requiring extended walking along public highway routes |
| Additional pedestrian crossings and exposure to live traffic introduced | Many passengers transfer without crossing live carriageways | Multiple signalised crossings required within Station Square and along Station Road, increasing exposure to moving traffic |
| Loss of enclosed, staffed 68-seat bus station environment | Sheltered, integrated, supervised waiting area with 68 enclosed seats, directly adjacent to the Underground | Dispersed on-street stops with partial or open-air shelters and no equivalent integrated waiting environment |
| Fragmentation of a single coherent interchange into dispersed street-based stops | Off-street, consolidated interchange with clear legibility and intuitive wayfinding | Looped island and dispersed on-street stops, reducing integration and increasing wayfinding complexity |
| Risk of permanent loss of 18 stand positions due to underground relocation without confirmed fire safety approval | 18 fully operational surface stand positions within an established bus station | 18 stands relocated into an underground EV garage dependent upon unresolved fire safety approvals; demolition of surface stands permitted before underground facility is demonstrably capable of lawful operation |
| Reduced operational resilience and increased stacking risk | Off-street layout avoids stacking onto Station Road and minimises signal conflict | Sequential stop–turn–crossing–stand–merge movements and termination constraints increase congestion and conflict risk |
| Disproportionate equality impacts arising from longer routes and fragmented interchange | Short, direct, step-free interchange benefiting mobility-impaired users | Longer walking routes, additional crossings and loss of sheltered waiting disproportionately affect disabled and elderly passengers (PSED implications) |