Ballymore's proposed 25 tower blocks over Edgware town centre

Application 24/2686/OUT — Ballymore & TfL

Official Objections & Evidence

Every statutory body that raised concerns — with direct links to full documents. Use this page to brief journalists, MPs, lawyers, or anyone who needs the facts quickly.

10+Official bodies raising concerns
7,000+Public objections — a Barnet record
6–3Council vote — all Labour for, all Conservatives against
£50k+Legal challenge being pursued

🔥 Fire & Safety — Statutory Bodies

2 submissions

LFB and HSE raised unresolved safety concerns about 190 electric buses beneath residential towers — concerns that remain live to this day

London Fire Brigade (LFB)

Serious concerns

Statutory consultee — raised concerns from 2022. Formal objection October 2024. Position reconfirmed July 2025 and at GLA Stage 2.

LFB first assessed the proposal in November 2022 and concluded it was "not viable as laid out." In its October 2024 formal objection, LFB warned of structural collapse risk to flats above the garage in an EV bus fire, toxic vapour cloud explosion risk, and inadequate fire access (road rated at only 12.5 tonnes — insufficient for firefighting vehicles). Nine tower blocks are structurally dependent on the garage below. LFB confirmed its objection was never withdrawn.

"The structural integrity of many of the blocks above the bus garage are intrinsically dependent on the structural integrity of the bus garage below... The potential for so many EV buses poses risks that are not fully understood by the industry at this point in time."

— London Fire Brigade, October 2024

Health & Safety Executive (HSE)

Gateway 1 concerns

Statutory safety consultee — Gateway 1 response, August 2024

Raised significant concerns about fire compartmentation, evacuation strategies, and fire service access in both the underground garage and the towers above it. Recommended critical safety flaws be resolved before the application progressed. Planning Condition 17 requires LFB sign-off before buses enter the garage — but does not prevent demolition of the existing station, construction of the towers, or occupation of up to 999 homes before that approval is obtained.

"These critical safety flaws [must] be addressed before the application progresses further."

— Health & Safety Executive, August 2024
Ballymore 25 tower block site plan

🏛️ Planning & Environment

4 submissions

GLA, Environment Agency, London Wildlife Trust and Barnet's own Trees and Heritage teams all raised objections

Greater London Authority (GLA)

Stage 1 — critical

Mayor of London's planning body — Stage 1 Report, September 2024

Stated the application "does not currently comply with the London Plan." Required the bus garage to be EV-ready from the outset. Found the replacement bus station inadequate — longer walk distances for passengers were identified as a strategic matter requiring resolution. Criticised the Equality Impact Assessment for excluding Harrow residents. Warned of increased collision risk from bus-turning movements.

Environment Agency (EA)

Formal objection

Statutory environmental consultee — August 2024

Formally objected due to flood risk from Deans Brook, insufficient flood storage, and inadequate sustainable drainage. Risks degrading water quality and harming protected species in the brook. EA's objection letter warned Barnet that approving the scheme without referring it to the Secretary of State would make the decision unlawful. The EA never withdrew its objection in writing.

London Wildlife Trust

Strong objection

Nature conservation body

Strong objections citing risks to Deans Brook Nature Reserve — a Borough Grade II SINC protecting bats, slow-worms, amphibians, and Schedule 1 birds including kingfisher and redwing. The Trust found the development fails biodiversity net gain requirements and called for a comprehensive ecological assessment. The approved scheme will open a formerly closed reserve to public access, introducing disturbance to species that have thrived precisely because of that closure.

Barnet Council — Trees & Heritage

Internal objections

Barnet's own internal consultees — two separate submissions

Trees: Removal of significant mature trees without sufficient replacement or long-term management plan. Fails London Plan Urban Greening Factor requirements.

Heritage: Towers undermine the setting of The Railway Hotel, St Margaret's Church, and Watling Estate Conservation Area. Negative impact on the character and appearance of listed buildings.

🏘️ Neighbouring Councils

1 submission

London Borough of Harrow formally objected, citing long-lasting impacts on its eastern and northern wards

London Borough of Harrow

Strong objection

Neighbouring borough — formal objection

Cited long-lasting impacts on Harrow's wards: traffic overflow into residential streets, added pressure on Canons and Stanmore stations, impact on Chandos Park flooding scheme, and the inadequacy of the replacement bus station. Also cited GLA Stage 1 negative response on the replacement bus station. Criticised the failure to conduct a cross-borough Equality Impact Assessment despite the development's direct impact on Harrow residents.

"LB Harrow strongly objects... and views the impacts to have long lasting impact on the eastern wards and northern wards."

— London Borough of Harrow
Save Our Edgware community campaign

👥 Community & Resident Organisations

4 document sets

ECA and SOE as designated non-statutory consultees, local associations, plus 7,000+ individual resident submissions — a Barnet record

ECA objection submission

Edgware Community Association (ECA) — Full Consultee Objection

Parts 1–4 · Non-statutory consultee representing all 5 Edgware wards

Four-part formal objection: design review failures and consultation failures (Part 1); transport, accessibility and Equality Act violations (Part 2); daylight, retail loss and fire safety strategy (Parts 3–4); and impact on Harrow's transport network.

📋

Save Our Edgware — Local Plan Objections

SOE-Objection01–07 · Barnet Draft Local Plan representations

Seven formal representations: Site 28 allocation, Site 27 density, transport policy GSS05, Major Town Centre misclassification, open space deficiency, and heritage protection.

🏙️

Local Residents' Associations — Independent Objections

Mill Hill Residents' Association · Canons Park RA · Canons Park Estate Ltd

Independent formal objections from local residents' associations and community groups across the wider area, raising concerns about density, design, transport impact, and the loss of local character. These submissions represent communities beyond Edgware ward itself, demonstrating the scheme's broad impact.

✍️

7,000+ Public Objections to Outline Application

Application 24/2686/OUT · Previous Barnet record was 2,500

Public objections covering fire safety, transport loss, retail loss, parking reduction, nature reserve damage, daylight loss, and Equality Act violations. 95% from local residents. Barnet's portal malfunctioned under the volume — yet still received a record number.

🚌 Transport & Accessibility

25×increase in bus-to-Tube walking distance — from 5m today to up to 132m under the scheme
145%increase in overall interchange walking distance (developer's own Transport Assessment)
165%increase in walking times for passengers with limited mobility
35.7%of interchange routes would require crossing the busy A5109 Station Road — vs 0% today
23,000daily bus passenger movements across ~20 routes — one of outer London's busiest interchanges

🌿 Nature & Environment

34%of Deans Brook Nature Reserve to be permanently lost — acknowledged as "Moderate Adverse (Significant)" in developer's own Environmental Statement
85%+shortfall in required green space (3.25ha vs 21.8ha needed for 10,900 residents)
1997Secretary of State ruling protecting Deans Brook from public access — being overridden
720homes allocated onto the nature reserve in the Local Plan — on land that Barnet itself says should be preserved

🏙️ Density & Daylight

23×denser than the surrounding Edgware context — one of the highest residential densities in the UK
50%+of windows in 176 neighbouring homes will receive inadequate daylight
48%reduction in A1 retail space — undermines Edgware's viability as a town centre
£41.5mof CIL public funds diverted to Ballymore — Barnet's own report says scheme is otherwise "not deliverable"

🔥 Fire Safety

190electric buses proposed beneath residential towers — a type of structure never built in the UK
0UK Building Regulations for underground EV bus garages — no framework currently exists
9tower blocks structurally dependent on the underground garage — per LFB's formal letter
999homes may be occupied above the garage before LFB fire safety approval is obtained — lawful under the permission as granted