Planning permission should be refused because the application does not comply with the NPPF, London Plan 2021, Mayor of London Transport Strategy, Barnet Local Plan 2012 and the Edgware Growth Area Supplementary Planning Document, June 2021, Equality Act 2010. The proposals do not comply with several principles of the SDP (4.1, page 25) and since they are interlocking does not meet the Principles in totality.
1 Edgware interchange, Bus Station, Bus Garage in Violations of Traffic Flow, Safety, and Accessibility Standards 2
2 Underground Bus Garage, a potential Fire Risk 9
3 Uncertain and Potentially Perpetual Interim Arrangements 9
4 Non-Compliance with the London Plan and Environmental Impact 9
5 Inadequate Planning for Continuity of Bus Services 10
6 Concerns About Alternative Plans (Plan B) 10
7 Inadequate catchment area for soliciting comments in proposed plan. 10
8 Developer has failed to properly engage with the public. 10
9 Developer has failed to engage meaningfully with local community groups. 10
10 Loss of Community Facilities for 5 years. 11
11 Negative impact on local economy & jobs for several years. 11
12 Proposed development will be the tallest and largest residential estate outside of central London. 11
13 Adverse wind effect. 11
14 Inadequate residents’ car parking space. 12
15 Grossly overestimated cycle parking space. 12
16 Increased risk to safety to public public safety during demolition and construction. 12
17 Inadequate accessibility considerations. 12
18 Deans Brook Nature Reserve, home to protected species, will be severely damaged by the proposed development. 13
19 Lack of Amenity Space Detrimental to Health and Wellbeing of Residents. 13
20 Plan underestimated the volume of vehicular traffic in the estate: 14
21 Lack of Consideration for the Impact of Nearby Developments. 14
22 Enhancements to Northern Line to cope with increased passengers’ volumes have not been considered. 15
23 Reduced Demand for Student Accommodation. 16
24 Developers Track Record on Large-Scale Developments. 16
25 Proposed Development Plan is not Financially Viable. 17
26 Heritage at Risk: Policy Violations and Threats to Edgware’s Character in the Ballymore Plan 20
1 Edgware interchange, Bus Station, Bus Garage in Violations of Traffic Flow, Safety, and Accessibility Standards
The proposals of the new bus stops (fig 3.16, proposed Development Bus Strategy Overview) to replace Edgware Bus station and the arrangement for bus operations, which has not been clarified, does not comply in any way with Public Transport Accessibility, Legibility and Capacity (SPD page 51), since the replacement is not a bus station. Interchange and has been made more difficult and dangerous for the public commuters. This is non compliant with the mayor of London’s transport strategy, policy 10,13,14, 15. The proposal is destroying a very good optimal interchange supported by an adjacent garage. This also means that it is non compliant with the Barnet Local Plan 2012. It should be noted that the destruction of the Bus station and garage is the direct result of Barnet Council, together with the GLA agreeing to build 2316 units on Site 28.
The proposals regarding the bus station and interchange as well as the car park have been stated by Ballymore LTD to be discriminating (Equality Act 2010) against people with the nine protected characteristics. We believe that It is unlawful for the applicants to put forward a proposal that is discriminatory. Also it is unlawful for Barnet council to grant planning permission so that Ballymore Ltd can discriminate.
The remedy is to keep Edgware Bus station and garage where it is but modernised to a standard providing a good safe public service space.
1.1 Congestion and Inefficient Bus Flow
The proposed Station Square Interchange presents multiple operational inefficiencies, which directly contravene policies outlined in the London Plan (Policy T2 – Healthy Streets and Active Travel) and the NPPF’s aims for sustainable transport:
- Frequent Stops: Buses will encounter four stop points in quick succession—turning into Station Square, waiting at two signal-controlled crossings, and turning back onto Station Road. This design will significantly slow down bus services, causing traffic backlogs. This is a violation of the London Plan’s directive for “promoting the smooth movement of public transport services” and Barnet’s Local Plan goal of minimising congestion to facilitate reliable bus services.
- Lane Merge Issues: The design creates a bottleneck by merging two lanes into one after the second pedestrian crossing, further delaying bus departures and increasing congestion. This will inevitably lead to bus backlogs, contradicting the NPPF’s commitment to ensuring that transport networks are safe, efficient, and accessible for all.
- Bus Stand Issues: The inadequate length of Stand F2, along with its proximity to pedestrian crossings, creates a safety hazard for passengers and pedestrians. The frequent obstruction of pedestrian crossings by buses waiting to depart highlights the failure to comply with the London Plan’s focus on safety in street design (Policy T2).

1.2 Pedestrian Safety Concerns
The new layout introduces significant pedestrian safety risks, violating both the NPPF’s safety provisions and Barnet Local Plan’s objectives for a safe, pedestrian-friendly environment:
- Buses Obstructing Crossings: The frequent obstruction of pedestrian crossings by queuing buses increases the risk of accidents and impedes the safe movement of pedestrians, in direct violation of the NPPF’s objectives for safe, accessible pedestrian routes and the London Plan’s focus on safe, healthy streets.
- Insufficient Sheltered Capacity: Limited sheltered areas at bus stands will result in passengers waiting under the Underground station canopy in bad weather, encouraging unsafe dashes across busy roads when buses arrive. This undermines the London Plan’s emphasis on providing safe, well-planned pedestrian environments and Barnet Local Plan’s commitment to improving pedestrian safety.
1.3 Accessibility Issues
The proposed design is highly problematic for disabled passengers, parents with young children, and elderly passengers, conflicting with key accessibility standards set forth in the London Plan, NPPF, and Barnet Local Plan:
- Increased Interchange Distances: The increased walking distance between bus stops and the Underground station (up to 150m in some cases) poses a significant challenge to passengers with mobility issues. This violates the London Plan’s focus on accessibility for all users (Policy T6) and the NPPF’s directive to create inclusive, accessible transport networks.
- Confusing and Unsafe Crossing Layouts: The poorly designed crossings at Station Square will create confusion for visually and hearing-impaired passengers, increasing the risk of accidents. This is a violation of the NPPF’s safety and accessibility provisions and contravenes Barnet Local Plan’s policies on safe pedestrian environments, particularly for disabled users.
- Inadequate Drop-Off and Pick-Up Facilities: The lack of proper drop-off/pick-up facilities, especially for taxis, further diminishes accessibility, in direct conflict with the London Plan (Policy T7 – Deliveries, Servicing, and Freight) and Barnet Local Plan’s aim of providing inclusive transport options for all users.

- Non-Compliant Parking Provision Violates London Plan and NPPF Accessibility Policies: The proposed parking arrangements for the residential area are inadequate for disabled users. With fewer than 400 spaces and located approximately 400m from the furthest residential block, this exceeds accessibility standards. BS 8300-1:2018 requires designated accessible parking spaces to be within 50m of an accessible entrance, making this design non-compliant. The distant location poses significant challenges for disabled residents, people with injuries, families with young children, and those carrying large items, severely limiting their access and convenience. Clearer provisions for accessible parking are essential to meet regulatory and community needs.
The proposed parking arrangement violates key policies in both the London Plan and the National Planning Policy Framework (NPPF) regarding accessibility and inclusive design:
- London Plan Policy T6.1 mandates that developments must provide parking for Blue Badge holders with spaces located close to building entrances, ensuring ease of access for disabled users. By placing accessible parking spaces up to 400m from residential blocks, this proposal directly contravenes the requirement for close proximity to entrances.
- London Plan Policy D5 outlines the need for developments to be inclusive and accessible for all users, particularly disabled people. The distant parking for disabled users fails to create an inclusive environment by limiting their access to homes, breaching this key policy.
- NPPF Paragraph 110(b) requires that developments prioritise safe and accessible spaces for all, particularly disabled individuals, through appropriate design. The long distance from parking to entrances does not meet the requirement for convenient and safe access for all users, violating this provision.

1.4 Impact on Bus Operations and Passenger Experience
The proposal also undermines the smooth functioning of bus services, which will directly affect bus drivers and passengers. This contravenes both the London Plan and Barnet Local Plan’s goals for enhancing public transport services:
- Outdoor Servicing for Electric Buses: Since the LFB has deemed the underground garage unsafe for electric buses, all maintenance and servicing will need to be done outdoors. This is inefficient and hazardous for staff, directly contravening the London Plan’s policy for high-quality, functional transport facilities (Policy T1).
- Impact on Routes and Potential Redundancies: There is a real risk that operational inefficiencies will lead to Edgware being abandoned as a bus depot, resulting in the loss of bus routes and potentially leading to redundancies. This directly opposes the London Plan’s call for enhancing public transport networks to meet growing demand.
1.5 Increased Traffic and Parking Challenges
The development introduces new traffic pinch points and worsens parking issues, violating key principles from the NPPF, London Plan, and Barnet Local Plan:
- Pinch Points and Congestion: Creating four pinch points where there was previously only one will significantly increase traffic congestion. Additionally, the reduction in available parking spaces and the narrowing of pavements directly contradicts the London Plan’s policies for reducing traffic congestion and improving the pedestrian environment (Policy T4).
- Insufficient Parking Provision: The minimal provision of five drop-off/pick-up spaces for the entire station is wholly inadequate. This will result in cars backing up onto Station Road, causing traffic chaos and raising the risk of accidents. The lack of sufficient parking and layby space violates both the NPPF’s provisions for transport infrastructure and Barnet Local Plan’s objectives to mitigate traffic impact and provide sufficient parking facilities.
1.6 Inadequate Support for Population Growth and Infrastructure Needs
The proposed development includes 25 new tower blocks but does not provide adequate infrastructure support for the increased population. This conflicts with the NPPF and London Plan’s sustainability guidelines:
- Overcrowded Public Transport: The development’s transport assessment fails to account for the increased population and its impact on buses and trains. This leads to concerns that public transport capacity will be insufficient, particularly during peak hours, violating the London Plan’s goals for supporting increased capacity on public transport systems (Policy T3).
- Parking and Access Shortfalls: The proposed parking provision is insufficient to meet the needs of both new residents and the existing population, which violates the NPPF and Barnet Local Plan’s policies for ensuring appropriate infrastructure support for new developments.
1.7 Flawed PTAL Assessment Fails to Address Wider Area Impact
The PTAL assessment in the transport report is limited to the development site, ignoring the lower PTAL levels in the surrounding Edgware area. Figure 3-11 shows a significant drop in PTAL in nearby areas, indicating a reliance on cars to access public transport. With reduced car parking spaces, this will worsen accessibility to Edgware Station, especially for those outside the immediate site. A broader assessment of transport access, including surrounding areas, is necessary to reflect the true impact.


2 Underground Bus Garage, a potential Fire Risk
We have discovered through a response to our FOI request that the London Fire Brigade stated firmly and comprehensively that this proposal is totally non viable as detailed below:
- The London Fire Brigade has assessed the proposal for an underground bus garage at Edgware requested by LB Tower Hamlets and came to the conclusion that it was not viable because of the impact of any fire caused by the lithium batteries in the electric buses catching fire. (FOI 7961.1 from London Fire Brigade about the scheme being non viable.) and articles published on The Daily Telegraph (Electric bus station fire could turn high-rise homes into ‘volcano’, residents warn) and The Sun (FIRE FEARS We’re terrified an EV charging hub will turn £1.7bn newbuild apartment blocks into a ‘VOLCANO’.), and the Barnet Post ( London Fire Brigade Edgware EV bus garage safety warning) on the Edgware Bus Garage fire risks.
- There are no standards for underground garages for electric buses and commercial vehicles and hence no Building Regulations (FOI response from OVEZ). Unless the science of lithium batteries changes, which is unlikely, within the terms of the development plan, it will be impossible to build an underground bus garage.
3 Uncertain and Potentially Perpetual Interim Arrangements
The proposed interim solution involves the construction of facilities to accommodate approximately 200 buses, along with associated maintenance and staff facilities, on a site occupying between two and three hectares of car parking space. There is a significant risk that these “interim” arrangements could persist indefinitely, leaving the scheme incomplete. This uncertainty is unacceptable, as it could result in a prolonged period of disruption and inadequate infrastructure.
4 Non-Compliance with the London Plan and Environmental Impact
The use of diesel generators and tankers as part of this interim solution poses a serious threat to air quality. This is in direct conflict with several key policies within the London Plan:
- Policy SI 1 (Improving Air Quality): This policy requires developments to not lead to further deterioration of existing poor air quality and to be “air quality neutral” or better. The reliance on diesel-powered generators would likely result in increased emissions, contrary to this policy.
- Policy SI 2 (Minimising Greenhouse Gas Emissions): This policy emphasises the need for developments to reduce greenhouse gas emissions in line with London’s target of becoming a zero-carbon city. The proposed interim solution does not align with this goal due to its continued reliance on diesel power, which is a significant source of carbon emissions.
- Policy T7 (Deliveries, Servicing, and Construction): This policy stresses the importance of reducing emissions from delivery and servicing vehicles, including buses, through the use of cleaner technologies. The use of diesel tankers and generators is inconsistent with this policy’s aim to reduce air pollution and promote sustainable transport solutions.
The application fails to demonstrate how it will mitigate these negative environmental impacts, making it non-compliant with these critical policies in the London Plan.
5 Inadequate Planning for Continuity of Bus Services
The application provides insufficient detail on how Transport for London (TfL) plans to maintain current levels of bus service during and after the interim period. Given the scale of the proposed arrangements, it is difficult to see how the existing level of service can be sustained, let alone improved. The lack of a clear, credible plan for service continuity is deeply concerning and raises questions about the viability of the proposal.
6 Concerns About Alternative Plans (Plan B)
There are concerns that TfL may have an alternative plan, potentially involving the use of a different bus garage. This scenario could lead to further disruptions and a “nightmare” situation where services are compromised. Alternatively, TfL could seek to justify the use of the unapproved bus garage under a force majeure clause, which would also be unacceptable.
7 Inadequate catchment area for soliciting comments in proposed plan.
Barnet council has only sent correspondences seeking comments to residences within 200 metres of the development. The proposed plan admits impact of demolition and construction dust beyond 200 metres by planning to monitor dust up to 350 metres from the site. (Figure 1, ENVIRONMENTAL_STATEMENT_VOL_3.04__AIR_QUALITY-6226643.pdf). Also, the “200 metres” catchment is not of proportionate size given the huge scale of the development and will effect far beyond the immediate neighbourhood, in contradiction to the NPPF guidelines. This area does not even cover Edgware Central Middle Layer Super Output Area (MSOA) or include any of the neighbouring Harrow residents. As with the consultation for the Edgware Local Area SPD Barnet consultation, the council appears to be only interested in conducting a “tick in the box” exercise rather than really caring what people have to say. A proportionate area to send letters, to ensure meaningful consultation, would be: Edgware – Barnet, Edgware – Harrow, Hale, Burnt Oak and Canons wards.
8 Developer has failed to properly engage with the public.
The Developer has a legal obligation, as per NPPF Section 4 & 12, London Plan Policy GG1 & D1 and Barnet Local Plan Policy DM14 & DM16, to properly engage with the public and adequately consider their feedback. They have taken little notice of the public feedback in its own organised survey by Commonplace Broadwalk. For example, most people strongly opposed the numerous tall towers being built – but the developer has instead increased the height of the towers, with the tallest one being 30 storeys instead of 29. They have also conveyed a very biased summary of the pre-planning feedback in its planning application, which does not at all reflect the true feedback of the local community!
9 Developer has failed to engage meaningfully with local community groups.
While they offered a meeting with Save Our Edgware, they restricted access to their partner, TFL, and refused to provide detailed information or address our questions. Since they refused to answer questions or share data that should have been public, Save Our Edgware declined the meeting, knowing it was just for PR purposes. This was not a genuine attempt at engagement by Ballymore.
The proposed plan indicates some meetings with church groups, but there is no mention of engagement with local Hindu or Islamic groups. Shishukunj is a local Hindu children’s charity, whose head office is located on the High Street, which has membership across Harrow and Mill Hill. Shree Swaminarayan Temple is a Hindu temple is Stanmore. There are also a couple of Islamic Centres nearby, one on High Street and one on Deansbrook Road. This means that Equality Impact Assessment is insufficient under the Equality Act 2010.
10 Loss of Community Facilities for 5 years.
The Broadwalk Centre, the cafe and bus station are communal areas serving as a vital social hub for people to gather, interact and access services. They provide warmth, shelter and inclusive spaces for diverse members of the community engendering community cohesion. Their loss of these facilities for 5 years will adversely impact community health and well-being, and is in contradiction to NPPF Section 8, London Plan policy S1 & GG1 and Barnet Local Plan policy DM13. This is also not in compliance with Principle 6 and 9 of the SDP.
11 Negative impact on local economy & jobs for several years.
The closure of the shopping mall, the reduced car parking and construction disruption lasting many years will drastically reduce the customer footfall leading to the closure of many high street stores & potentially reduce services such as banks and building societies. This will have a significant adverse impact on the local economy. Retail jobs will be lost, as staff will look for work in other areas. The economic health of the town centre will be undermined contrary to NPPF Section 6, 7 & 15, London Plan Policy E1, T7 & SD6, Barnet Local Plan Policy D11 & CS6.This is not in compliance with Principle 7 of the SDP. The proposed new jobs set out in the proposal will not compensate for these losses.
12 Proposed development will be the tallest and largest residential estate outside of central London.
The development will have the tallest and largest number of high-rise buildings outside of central London. Currently Croydon Tower which is 135 metres tall, is the tallest outside central London. The proposed development will have 11 towers higher than the Croydon Tower. The largest residential estate currently in London is Aylesbury Estate in Southwark, with 2,700 dwellings and circa 7,000 residents. The proposed development in Edgware will surpass this, with a capacity of 10,900 residents, and is totally out of character in this suburban neighbourhood.
13 Adverse wind effect.
The numerous tall buildings, up to 30 storeys high, will create a serious wind tunnel effect. It will make unsafe any balconies in this very windy environment. Tall buildings also have a tendency to sway in strong winds, creating anxiety and motion sickness. There is a risk to the public and residents from wind which the developer/ council could be liable for. The adverse wind effect of the proposed development is in contradiction to NPPF Para 103 & 131, London Plan Policy D9 and Barnet Local Plan Policy DM05 & Draft Policy BSS01
14 Inadequate residents’ car parking space.
A total of 371 residential blue badge parking spaces are proposed. Leaving no other parking spaces specifically for residents; they will have to spend hours looking for parking in the neighbour streets in the short term Sainsbury car park. Beyond this there is no parking space allocation for staff/ workers within the commercial/ retail units on site. As acknowledged in the 2020 Draft Barnet Local Plan, there continues to be high car usage in this borough which has not been taken into account. While the site is near an end of line tube station and bus station, it is unrealistic to believe that residents and commuters will not wish to own a car. Lateral cross-borough transport is a challenge in Barnet, as it is in all suburbs. The fact that residents are unable to access easy public transport that traverses east to west is a further reason to expect that many thousands of residents could move into this new development wanting their own cars. The parking deficit will also cause overflow into neighbouring areas, as already observed with residents of Premier Place, which is only one block of 17 floors..
15 Grossly overestimated cycle parking space.
It is unrealistic to expect families with young children (21% in Barnet) and the elderly (15% in Barnet) and the disabled (7% in Barnet) to use cycles. Additionally, as there are only a few streets with cycle paths and many of these are narrow, making it very dangerous to cycle.Those more mobile folks will not want to cycle. This is demonstrated by only circa 3% of trips being made by cycling in Barnet. Hence the proposed cycle space of at least 6,655 is a gross over-estimate.
16 Increased risk to safety to public public safety during demolition and construction.
As an example, the Station Square interchange will potentially endanger pedestrians. With approximately 23 bus routes, blocking pedestrian crossings while waiting to turn from the Station Square interchange onto Station Road, will cause congestion endangering pedestrians, including many school children using buses and the tube. Insufficient shelter capacity at stands D2, F2 & G2 c) Stand GS2 has capacity to hold only one bus, whilst five routes use this stand. If a second bus turns up it will block the pedestrian crossing and the road. This is in contradiction to NPPF Para 110 & 111, London Plan Policy T2 & T7, Barnet Local Plan Policy DM17, Barnet Development Management Policies DPD Policy DM01 Concerns. This is not in compliance with Principle 2 of the SDP.
17 Inadequate accessibility considerations.
The proposed plan fails to properly address the needs of disabled people, families with children and the elderly. For example:
- a) Residential MSCP is located almost 400m from the furthest residential block
- b) Some bus stops will require people to cross the street to access the new interchange creating additional risk for those visually/ hearing impaired
- c) Shared paths with cyclists creating a hazard for pedestrians and especially visually/ hearing impaired folks
- d) Minimum widths for evacuation routes are insufficient for wheelchair users d) The loss of the car turnaround at Edgware station will also cause significant hardship to those with mobility issues, and, the many people who arrive or depart from the station with large bags and luggage
- e) During construction relocation of the bus stands away from the Tube Station to Station Road and southeast corner of the site, will increase the walking distance to the interchange and also past the noisy construction site
- f) Accessibility will become more difficult during the construction by having blocked sidewalks & detours.
- g) Increased noise & activity during construction will impact those with neurosensory disabilities.
This is in contradiction to Equality Act 2010, London Plan Policy D5 & D7 & Barnet Local Plan Draft Policy CDH01 and Barnets Development Management Policies DPD Policy DM03. This is not in compliance with Principle 2 of the SDP.
18 Deans Brook Nature Reserve, home to protected species, will be severely damaged by the proposed development.
Contrary to NPPF policies the development will not enhance local biodiversity, and in fact will endanger the biodiversity that has developed over many decades. Out of about 2.6 hectares of habitat area and trees within 0.87 hectares, around 34%, will be lost, to build two paths, 4 metres wide, for walkers and cyclists. This will divide the area into two, separated by a hard surface. The lighting needed to make this path safe will affect bats and other nocturnal creatures currently living there. Opening up the nature reserve will also provide secluded opportunities for mis-behaviour including mugging, drug taking, littering and fly-tipping, which are already issues in local parks. You only have to see the problems in the small childrens play area a few metres away near Brook Avenue. Additionally, plans to divert rain water to Deans Brook, risk polluting the ecosystem and endangering these protected species and their habitats. This is not in compliance with Principle 8 of the SDP. This is a violation of Barnet Council’s statutory duty of care for Biodiversity under Section 40 of the Natural Environment and Rural Communities Act 2006.
The Bio Diversity Net Gain Report has not surveyed the presence of animal species in the SNIC. Only the biodiversity of plant species has been considered and the presence of animal biodiversity has NOT been taken into account. It is common knowledge that the SNIC is the habitat of many protected animals. Hence the resulting conclusion that the Illustrative Scheme can achieve a Biodiversity BNG value of 10% is flawed. Additionally the Statutory Biodiversity Metric Calculation Tool states the ‘area created does not equal the area lost’ relating to the area of broadleaved woodland which is being removed!
19 Lack of Amenity Space Detrimental to Health and Wellbeing of Residents.
The development offers very limited public park space due to economic pressures to maximise housing units. The proposed Fairfields Play Park is not large enough to be considered to be a playground for the whole of Edgware, as conveyed in the plan. Also, Edgware Gardens, a space reserved for residents, is too small given the number of residents.
20 Plan underestimated the volume of vehicular traffic in the estate:
The proposed plan underestimates the volume of vehicular traffic that will be generated by the estate, which could lead to substantial challenges for both residents and the surrounding community. The current analysis is flawed as it focuses primarily on the number of vehicles within the site, rather than the number of journeys to and from the site. This is a crucial oversight, as it fails to identify potential bottlenecks both on the estate and on Church Way, where traffic is likely to become heavily congested. This is not in compliance with Principle 2 of the SDP.
The plan appears to underestimate the frequency and impact of Heavy Goods Vehicles (HGVs) and Light Goods Vehicles (LGVs) visiting the site. Additionally, several important categories of traffic have been overlooked, including vehicles needed for the maintenance and servicing of on-site buildings, commercial waste collection, and Transport for London (TFL) vehicles. Also, there has been no comprehensive analysis of the on-site traffic generated by daily activities such as Sainsbury’s shoppers using the car park, residents accessing residential parking, food delivery services, parcel deliveries, and taxis regularly called upon by residents and visitors. The combined impact of these activities is estimated to involve over 25,000 vehicles journeys per week, a significant volume that has not been considered.
The plan also neglects to fully address other forms of traffic, including buses using the underground bus station and cyclists navigating the estate. The laybys are likely to become congested, with taxis, parcel deliveries, and food delivery vehicles all competing for space. This could create, potentially, hazardous conditions, particularly for pedestrians who will need to be cautious around these busy areas.
For residents and visitors looking to enjoy the estate’s green spaces, the reality may fall short of expectations. Instead of a peaceful environment, they may be exposed to traffic noise and pollution. Those living on lower floors or using their balconies will likely experience the impact of increased traffic throughout the day, with noise and emissions potentially affecting their quality of life. At night, the quieter surroundings may amplify the noise from HGVs and LGVs, further disrupting residents’ rest.
The high volume of traffic using Church Way, combined with the estate’s traffic, is expected to cause severe congestion. This congestion will likely extend to Station Road and the High Street, leading to traffic issues across a wider area.
21 Lack of Consideration for the Impact of Nearby Developments.
The proposed plan for the Edgware development appears to have been compiled in a vacuum, with little to no consideration given to the numerous large-scale mixed-use and residential developments that have already been completed, and are currently underway, or are planned in nearby towns such as Colindale, Burnt Oak, Hendon, Brent Cross, and Wembley. These surrounding areas not only offer comparable housing options but, in many cases, surpass what is being proposed for Edgware. For instance, Brent Cross is home to a massive, well-established shopping mall, providing amenities that the Edgware development cannot match. Additionally, property prices in some of these neighbouring areas are more affordable than those forecast for Edgware, making them more attractive to potential buyers and renters.
The failure to account for these nearby developments is a glaring oversight that could have serious repercussions for the success and sustainability of the Edgware project. Specific areas of concern include:
- Northern Line Capacity: The cumulative strain on the Northern Line, with additional residents from these nearby developments, will likely lead to overcrowding and negatively impact daily commuters.
- Bus Capacity: The increased population in the surrounding areas will inevitably put pressure on bus services. Without a clear plan to enhance bus capacity, the proposed development could exacerbate transit issues, leading to longer wait times and overcrowded buses.
- Footfall in Edgware Centre: With nearby areas offering more amenities and attractions, Edgware Centre may struggle to draw the predicted footfall. This could result in lower-than-expected shoppers activity, undermining the vibrancy and economic viability of the area.
- Impact on Selling or Renting Flats/Commercial Units: The oversupply of housing and commercial space in the region, combined with more competitive pricing in neighbouring areas, could lead to reduced demand for the properties in Edgware, and threatens the financial viability of the project.
- Strain on Infrastructure and Services: The influx of new residents across these developments will inevitably place a heavy burden on local infrastructure and public services. Without coordinated planning, this strain could lead to a decline in the quality of life for both current and future residents of Edgware. This is not in compliance with Principle 2 and 7 of the SDP.
22 Enhancements to Northern Line to cope with increased passengers’ volumes have not been considered.
The proposed development plans along the Northern Line, particularly between Camden Town and Edgware, including significant building projects at Edgware, Colindale, Brent Cross, and Hendon, necessitate comprehensive infrastructure enhancements to manage the anticipated surge in passenger numbers. Without these upgrades, the service quality could degrade, leading to overcrowding and delays. This is not in compliance with Principle 2 of the SDP.
Edgware, Colindale, Hendon, and Brent Cross stations may require expanded concourses, additional ticketing facilities, and improved pedestrian flow management to handle the increased footfall. This could involve installing more ticket machines, widening gates, and improving wayfinding signage. Enhancing accessibility through upgraded lifts and escalators is also critical to ensure the network remains usable for all commuters, including those with mobility challenges. The current major upgrade work to Colindale Station is funded by Government’s Leveling Up Fund, and hence this funding could be requested for Edgware Station as well. This is not in compliance with Principle 2 of the SDP.
23 Reduced Demand for Student Accommodation.
Anticipated visa restrictions targeting students, along with increased competition from nearby developments, are expected to lower the demand for student accommodation. The visa restrictions could result in fewer international students from countries like China and Nigeria, which will mean reduced spending, than forecast, on housing, food, transportation, and other living expenses, negatively impacting local businesses.
Since student accommodation is not typically suitable for housing the general population, conversion would be necessary. This would involve significant work, including regulatory compliance and planning approval. Potential conversion options include merging two student studio units into a single regular studio or combining two 1-bedroom student units into a regular 1-bedroom apartment. The changes would require structural modifications, upgrades to plumbing and electrical systems, improved finishes, and fire and safety system enhancements. The estimated cost for these conversions ranges between £30,000 and £50,000.
24 Developers Track Record on Large-Scale Developments.
Ballymore has a poor track record with large projects like Royal Wharf and Bishopsgate Goodsyard. Their lack of foresight in design and inadequate community engagement led to significant challenges. These failures resulted in delays, escalated costs, and in the case of Bishopsgate Goodsyard, a drastic reduction in the scope of the project. Many of the issues highligthed below and the resulting lessons learnt are applicable to the Edgware Broadwalk project.
- Design and Planning Failures: Royal Wharf: Ballymore’s original design was flawed, lacking consideration for the project’s density and its impact on local amenities. Their oversight required multiple revisions, delaying the project and forcing them to retroactively add necessary community facilities and green spaces. Bishopsgate Goodsyard: Ballymore’s failure to account for the site’s historical significance and the scale of the development led to widespread opposition. Their initial proposals were so out of touch with the area’s character that they had to be extensively redesigned, including significant reductions in building heights and the addition of public spaces.
- Infrastructure and Service Provision Failures: Royal Wharf: Ballymore’s inadequate planning for essential infrastructure like transportation, schools, and healthcare from the outset caused major delays. The lack of foresight required the project to be phased and reworked, leading to further setbacks. Bishopsgate Goodsyard: Ballymore’s failure to address the strain that their development would place on local infrastructure was a major oversight. This negligence forced a scale-back of the project after it became clear that existing services couldn’t support their initial plans.
- Failures in Community Engagement: Royal Wharf: Ballymore failed to engage the local community effectively, leading to opposition that delayed the project. They were forced to revise their plans after approval, wasting time and resources that could have been saved with better initial engagement. Bishopsgate Goodsyard: Ballymore’s inadequate consultation with local residents resulted in strong community resistance, including protests and legal challenges. Their disregard for local concerns led to years of delays and eventually forced them to make significant concessions.
- Cost Overruns and Delays: Royal Wharf: Ballymore’s lack of proper planning led to cost overruns and extended timelines. Their decision to phase the project, due to unforeseen site conditions and necessary redesigns, further exacerbated the delays. Bishopsgate Goodsyard: Ballymore’s mishandling of the planning process resulted in significant delays and likely cost overruns. The project approval was delayed by years, primarily due to their failure to adequately address planning and community concerns.
- Scaling Down of Original Requirements: Royal Wharf: Due to Ballymore’s inadequate initial design, the project had to be adjusted to better integrate with existing infrastructure and meet community needs. Although the project was completed, it required significant modifications. Bishopsgate Goodsyard: Ballymore’s unrealistic original plans had to be significantly scaled down after they failed to consider community and planning requirements. The final development was a shadow of the original proposal, with reduced building heights and more public space, to mitigate the issues Ballymore initially ignored.
25 Proposed Development Plan is not Financially Viable.
The project is projected to be loss-making and predicted to be straddled with a debt of £500m upon completion. Even before the project starts the developer is already requesting a “bailout” from LBB and GLA. This does not instil any confidence in the viability of the project.
The financial viability assessment submitted with the proposed development plan is fundamentally flawed due to its incomplete analysis, unrealistic assumptions, and omitted costs. The “rough and ready” analysis does not provide a sound financial basis for approving the proposed development. A thorough re-evaluation is necessary, incorporating detailed and accurate financial projections, proper risk management strategies, and up-to-date cost estimates.
Key concerns and inaccuracies are outlined below:
25.1 Financing Concerns
- Inadequate Financing Rate Assumption: The development is entirely debt-financed, necessitating a robust cash flow to service the debt, even during loss-making periods. However, the financial viability assessment assumes an unreasonably low financing rate of 8.5%. For a long-term, high-risk project like this, a more realistic rate would be closer to 12.5%, as cited in the financial documents. Interest rates are likely to fluctuate due to economic factors such as inflation, the cycles of recession and boom, and credit market conditions. If the developer opts for fixed-rate financing to secure costs, the interest rates will likely be higher. With only a 5% contingency, any minor financial disruption could lead to difficulties in meeting debt obligations, significantly increasing the risk of default.
- Subsidy Dependency: The project is already projected to be loss-making, and its reliant on subsidies adding further financial uncertainty. The developer is seeking funding specifically for the affordable housing component. The London Plan Threshold Approach to Applications Policy H5, stipulates a minimum of 35% housing needs to be Affordable, without public subsidy. The plan is in contradiction to this – with plans to provide 35% affordable housing and developer asking for a subsidy! Subsidies are contingent on approval processes and susceptible to policy changes, and they may not cover unexpected costs. If subsidies are delayed or insufficient, the project could face significant financial challenges. Given the incomplete and inaccurate financial modelling (see below comments), it is likely that the developer will request additional “bailouts” during the project’s lifecycle. With both LBB and GLA committed to the project, they may feel compelled to provide this funding to avoid the embarrassment of scaling back or cancelling the project.
- Debt of £500 million estimated at end of construction: A rudimentary cash flow analysis (reference: Figure 2 in FINANCIAL_VIABILITY_ASSESSMENT__PART_01-6225081), shows a substantial debt burden of £500 million still outstanding at the end of construction. At this stage with only income from commercial rental and service charges, it is uncertain how this will be paid off, unless the developer is expecting this will be paid off by LBB & GLA!
25.2 Rudimentary Financial Analysis
- Lack of Full Life-Cycle Modelling: A thorough financial analysis should include full life-cycle modelling. The submission only provides a rough cash flow (reference: Figure 2 in FINANCIAL_VIABILITY_ASSESSMENT__PART_01-6225081), showing a substantial debt burden of £500 million still outstanding at the end of construction.
- No sensitivity analysis has been conducted to examine how changes in key assumptions, like sales values, construction costs etc, will affect the viability of the project. Hence it is not possible to determine the robustness of the proposed development under different market conditions.
- Inflation Considerations Ignored: The financial assessment fails to account for inflation over the 13-year construction period, leading to an unrealistic view of material, labour, and other costs. The rudimentary analysis provided suggests that if price growth exceeds inflation, the project could yield some profit, but this is not a comprehensive or reliable forecast (Reference: Table 8 – Growth & Inflation in FINANCIAL_VIABILITY_ASSESSMENT__PART_01-6225081).
- Inadequate Property and Rental Market Analysis: The assessment lacks any modelling of future property price trends and commercial rental values. It also fails to consider potential fluctuations in residential property demand, which could be impacted by changing government regulations.
- Absence of Risk Management Strategy: There is no comprehensive risk management strategy in place, and minimal risk analysis has been conducted. Without an understanding of key risks, their likelihood, impact, or mitigation strategies, the project is vulnerable to unforeseen challenges.
25.3 Risk that Community Levy Payments May Not Deliver Expected Infrastructure or Facilities
The draft Planning Obligations SPD July 2024 allows developers in certain areas to pay a levy to the local council instead of directly providing the necessary infrastructure or facilities, such as affordable housing, employment opportunities, community facilities, open space and play areas, environmental sustainability measures, trees, and biodiversity enhancements. However, paying a levy does not guarantee that Barnet Council will deliver these related facilities, especially within easy reach of the development. Given the financial pressures many councils face, there is a concern that this levy income might be diverted to cover other borough expenses. This poses a risk that the development may result in reduced affordable housing, fewer job opportunities for Barnet residents, loss of community facilities, and diminished or overcrowded open spaces and play areas.
The Draft Planning Obligations Draft SPD stipulates for major developments 20% of the labour needs to be local and 10% of the supply during construction needs to be based in Barnet. The plans fail to indicate how this will be fulfilled or the practicality of meeting these targets. Additionally there is no indication of how this will be monitored independently.
The Draft Planning Obligations Draft SPD stiplates the provision of replacement community facilities of an equivalent or better quality to continue to serve the needs of the community. There will be no replacements for community facilities like the sheltered bus station or covered shopping centre for many years of construction and potentially afterwards!
Additionally, there is widespread concern about the lack of transparency in how planning obligations are negotiated and implemented, as well as the limited public involvement in these processes. This has led to scepticism about whether the community’s best interests are truly being considered and served. We have already experienced some lack of transparency where Barnet Council have refused to share information requested through the FOI process.
25.4 Inaccurate Assumptions
- Unrealistic Contingency Budget: A 5% contingency budget is insufficient for a large-scale, 13-year development, especially one that is 100% debt-financed and lacks inflation adjustments or detailed plans. A more realistic contingency would be in the range of 15-20%. The current contingency level increases the risk of default if any financial issues arise.
- Over-Optimistic Commercial Rental Assumptions: The financial assessment assumes no void periods for commercial rentals, leading to an overly optimistic revenue forecast.
- Out of date Cost Assumptions: The assessment assumes costs from Q2 2023, which will be outdated by two years by the time the development begins in 2025. This further undermines the financial projections.
- Contractor costs underestimated: All work is expected to be subcontracted out. The contractors will definitely include their management overheads, allowance for making profit & contingency in any quotes given. As only standard labour rates have been assumed in the costing, this additional contractor costs will cause at least a 25% uplift of the costs.
25.5 Costs Omitted
- Emerging Requirements: Costs associated with meeting new fire safety and sustainability requirements have not been defined or included.
- Fire Safety Compliance: The assessment excludes provisions for staircase pressurisation, which is a requirement under fire regulations.
- Temporary Bus Depot: The methodology and design for the temporary bus depot have not been finalised, and costs for fit-out have been explicitly excluded.
- Refurbishing Edgware Station Ticket Hall: This is vital given the increase in expected passenger volumes. The current major upgrade work to Colindale Station is funded by Government’s Leveling Up Fund, and hence this funding could be requested for Edgware Station as well.
- Operational Costs: No operational costs, such as site management & building maintenance, have been estimated although these will start to be incurred as soon as Phase 1 is delivered.
- Sales & Marketing Costs: These have been omitted from the financial viability assessment.
- Building Maintenance Units (BMUs): There is no provision for BMUs in the cost estimates.
- Rainwater Recycling: Rainwater recycling has been omitted with the possibility of revisiting the omission if required.
- Blue Roofs: sustainable roofing solutions are not included in the base design.
- Acoustic Provisions to Northern Edge Façade.
- Project Management: Costs have been omitted, although this role is essential given the size and nature of this development
25.6 Costs Roughly Estimated
- Infrastructure & External Works: The estimates for infrastructure and external works are based on outdated advice and lack detailed design information.
- Green Roofs and PVs: The extent of green roofs and photovoltaic systems required is uncertain, leading to potential underestimation of costs.
- Nature Reserve: The work required for landscaping and pathways in the nature reserve has not been detailed, resulting in rough cost estimates.
- Bus Depot Wall Structure: The wall structure along the perimeter of the bus depot and southern blocks has yet to be confirmed.
- Podium: Limited information is available for the podium, leading to rough cost estimates.
- Residential Blocks: Costs based on general block layouts, areas, and the number of storeys/units without specific design details.
- Landscaping: Cost allowances for landscaping are based on the current strategy but are provisional and subject to change as the design evolves. Specific elements like play equipment, street furniture, and external lighting have been measured and costed but could change.
- Utility Trench: Allowance made for a utility trench based on advice and details are still to be confirmed.
- Foundations and Structural Design: Rebar allowance and core walls adapted based on advice, but column layout details for residential blocks are not provided, so allowances remain generic.
- Façade: Façade costs adapted based on recent VE exercise. Rates are applied to blocks of different heights, but allowances are provisional.
- Apartment Fit-Out Specification: No specific details available for the internal fit-out, so costs are modelled on past projects.
- Affordable Housing Fit-Out: Fit-out priced at a lower level than private units, but specific requirements are not detailed.
26 Heritage at Risk: Policy Violations and Threats to Edgware’s Character in the Ballymore Plan
The Ballymore Plan not only threatens Edgware’s unique heritage and suburban character but also violates multiple national, regional, and local planning policies aimed at protecting heritage assets, preserving local character, and ensuring community involvement. The harm to Edgware’s historical assets and identity is not justified by the minimal public benefits offered, leading to a clear conflict with NPPF, London Plan, and Barnet Local Plan policies. The development must be reconsidered to align with these policies and to preserve the historical and architectural integrity of Edgware.
- Misrepresentation of Heritage Value: Ballymore’s heritage assessment downplays the significance of Edgware’s key heritage assets, such as the Railway Hotel and Edgware Station. The assessment rates these assets as having low to medium heritage value, which undermines their historical and architectural importance. This misrepresentation violates NPPF Paragraph 208, which states that any harm to heritage assets, even if “less than substantial,” must be weighed against public benefits. The proposal fails to demonstrate adequate public benefits to justify the harm caused.
- Violation of Suburban Character Policies: The high-density development contradicts policies designed to preserve Edgware’s low-density suburban character, particularly London Plan Policy D1, which mandates that development must respect and enhance the local context. The plan’s disregard for Edgware’s suburban identity also breaches NPPF Paragraph 203 (c), which emphasizes the importance of new development contributing positively to local character and distinctiveness. This proposal does neither, resulting in overdevelopment that fundamentally alters the low-rise nature of the area.
- Public Benefit Shortfall: The National Planning Policy Framework (NPPF) Paragraph 208 requires that harm to a designated heritage asset be justified by public benefits. The Ballymore Plan offers minimal public benefits, such as potential improvements to public spaces, which are vastly outweighed by the damage to Edgware’s heritage. This failure to deliver adequate public benefit violates NPPF Paragraph 208, which demands that any development leading to less-than-substantial harm should offer clear public benefits in return.
- Failure to Protect Townscape and Visual Integrity: The proposed high-rise towers would dominate the local skyline, overwhelming existing heritage assets such as St. Margaret’s Church, the Railway Hotel, and the Parish Church of St. Margaret. These impacts violate London Plan Policy D9, which requires that tall buildings respect the townscape and avoid visual harm. Furthermore, London Plan Policy HC1 (C) mandates that developments affecting heritage assets must conserve their significance and be sympathetic to their surroundings. The proposed towers fail to meet this requirement, dramatically altering Edgware’s townscape and disconnecting heritage assets from their historic context.
- Inconsistent Heritage Methodology: Ballymore’s methodology in assessing the heritage impact selectively supports the development, neglecting important documents like the Characterisation Study of Barnet Sections 1-6, which identifies Edgware as a low-density suburban area. This failure to consider key studies undermines the credibility of the assessment and violates NPPF Paragraph 200, which requires developers to provide a thorough and accurate description of heritage assets and their significance.
- Impact on Visual Identity and Setting of Heritage Assets: The visual impact of the proposed development on important heritage assets, including the Railway Hotel, Edgware Station, and St. Margaret’s Church, is understated in Ballymore’s assessment. The Built Heritage, Townscape, and Visual Impact Assessment document fails to properly account for the significance of these assets’ settings, which are integral to their heritage value. This violation of NPPF Paragraph 209 emphasises the need for careful consideration of non-designated heritage assets and their settings, which Ballymore’s proposal disregards.
- Failure to Align with Local and Regional Planning Policies: The proposal contradicts numerous policies within the Barnet Local Plan (2012) and the Edgware Growth Area Supplementary Planning Document (SPD) (June 2021), which call for careful management of development to preserve the suburban character of Edgware. The development also violates London Plan Policy D1 (parts A and B), which stresses that growth should align with the character and form of the area. By pushing for an excessive density that does not fit within Edgware’s infrastructure or character, the Ballymore Plan fails to meet these critical local and regional policy standards.
- Disregard for Resident and Public Opinion: The London Plan Policy D1 (B; 3.1.3) requires developers to involve a wide range of people in understanding how places are perceived, experienced, and valued. Ballymore’s failure to meaningfully engage with the local community and its dismissal of public feedback violate this policy. Most local residents oppose the high-rise development, which they view as incompatible with Edgware’s heritage and suburban nature.
- Undermining of Local Historical Significance: The proposed development does not respect the town’s rich history and identity, which have developed over centuries. Edgware’s heritage as a low-density residential suburb with notable architectural assets is not sufficiently acknowledged in Ballymore’s planning documents. This failure violates London Plan Policy HC1 and the Characterisation Study of Barnet, which both emphasise the preservation of local character and the importance of heritage in defining an area’s identity.