Barnet Strategic Planning Committee Decision to Approve Outline Application 24/2686/OUT
On 24 March 2026, Barnet's Strategic Planning Committee resolved to approve the outline planning application submitted by Ballymore for a major mixed-use redevelopment of Edgware town centre, including the addendum papers and a draft Section 106 agreement.
Background
The outline planning application for a large-scale mixed-use development at Edgware town centre was submitted by Ballymore Group. The scheme proposes approximately 3,800 or more residential units across roughly 8 hectares, alongside commercial uses, and includes the removal of the existing Edgware bus station.
The application has been subject to extensive representations, including detailed objections submitted by the Edgware Community Association and Save Our Edgware, covering transport modelling, fire safety, heritage, environmental impact, and housing mix concerns.
Note on the addendum papers: The committee considered an addendum to the July 2025 officer report, circulated on 24 March 2026. The addendum addressed updated conditions, the draft Section 106 heads of terms, and officer responses to representations received since the original report.
The Section 106 agreement sets out obligations in respect of affordable housing, transport contributions, public realm, and other planning requirements attached to the outline permission.
The resolution to approve is subject to the completion of the Section 106 legal agreement. Formal grant of permission will not be issued until that agreement is executed. Reserved matters applications will follow for each phase of development.
Committee Papers & Documents
The following documents were before the committee on 24 March 2026 and are available via the London Borough of Barnet planning portal and the shared document folder below.
What Happens Next
The committee's resolution to approve does not constitute the formal grant of planning permission. The following steps remain before permission is formally issued and before development can commence:
1. Execution of the Section 106 agreement. The legal agreement must be signed by the applicant and the London Borough of Barnet. Until executed, permission cannot be formally granted.
2. Formal decision notice. Once the Section 106 is completed, Barnet will issue the outline planning decision notice with conditions attached.
3. Reserved matters applications. The outline approval covers principle, layout, scale, appearance, and access in general terms. Detailed reserved matters applications will be required for each phase before any construction commences on that phase.
4. Pre-commencement conditions. A number of conditions will require discharge by Barnet before any works begin on site. These will include transport, ecology, drainage, and heritage conditions.
ECA & Save Our Edgware position: The Edgware Community Association and Save Our Edgware maintain that the concerns raised in their detailed objections — including transport modelling accuracy, bus station provision, fire safety access, affordable housing delivery, and heritage impact — have not been adequately addressed. These matters will continue to be pursued through the reserved matters, condition discharge, and Section 106 monitoring processes.